Background 

Schema changes are always made synchronously when Mattermost starts up. This means the application won’t be ready to serve requests until all schema changes are applied. In most cases, the new application won’t be able to work until those schema changes are in place.

If your migration will take more time on a larger data set, check if it is possible to extract it as a separate SQL query for the customer to run off-hours on their DB. This is usually possible with new indexes/columns. As a result, when the application is upgraded, the migration is a no-op because those columns/indexes are already added.

The problem arises when in some databases, for some tables, due to various technical reasons, applying a migration prevents other operations from happening on that table. In that case, it causes unavoidable downtime.

TLDR 

  1. Migrations are always synchronous.
  2. The time taken to run a migration is not always the primary factor in judging impact.
  3. Except in cases where a migration cannot run concurrently with other database operations.

I need to make a schema change. What do I do? 

  1. Every store is initialized in a newXXXStore function in store/sqlstore/XXX_store.go file. It should have a db.AddTableWithName call. Add your column to that table with the right ColMap param. Add other constraints as necessary.
  2. Modify the store/sqlstore/upgrade.go file. Scroll to the bottom, and add your migration there. (This method is going to change in the near future).

How do I measure the impact of the migration? 

Answer the following two questions:

  1. Is it a large table (like Posts or ThreadMemberships)? (The performance team can help you with this.)
  2. Can my change run concurrently with other database operations in that table? Check MySQL and PostgreSQL documentation, starting from required minimum versions supported by Mattermost.

If the answer to 2. is yes, then it should be pretty simple. In that case, if the answer to 1 is also yes, then please extract the raw SQL query to be run and add it in the release notes for customers who want to run it in off-hours to speed up upgrade time.

However, If the answer to the second question above is “no”, then contact the performance team to discuss a solution.

Inform SRE team. 

If the migration is large, when the PR is review complete, please cc an SRE team member and ask them to merge it and their convenience. This is so that the migration can run on our Community cluster and Cloud at a suitable time.